Location
|
Forest North neighborhood
|
Description
|
The project consists of local drainage improvements in the Forest North neighborhood. Design and construction are being completed by zone as funding becomes available.
Phase 2
There are a total of six work zones in Phase 2. A map of the neighborhood and work zones can be found in the "Project Zone Map" under Documents.
Phase 3 There are a total of seven work zones in Phase 3. A map of the neighborhood and work zones can be found below.
|
Status
|
Phase 3: Design work for the Phase 3 drainage improvements is nearing completion by K Friese & Associates. AT&T relocations have been completed throughout the neighborhood. Funding for the construction of Phase 3 has not been identified. When funds become available, work in Phase 3 will proceed. Construction for Anderson Mill in Phase 3 started in April 2019, and is anticipated to be complete fall 2019.
Phase 2: Construction was completed by DeNucci Constructors LLC on November 2, 2017.
Phase 1: Zones to be completed by Williamson County Road and Bridge:
Work in the Bayswater Zone has been completed by Williamson County Road and Bridge. Anderson Mills in Phase 3.
|
Contact
|
Email [email protected] or phone 512-943-1195 or if you'd like to subscribe for updates click here
|