Location
|
Ronald W. Reagan Blvd., North Phase 1 (formerly known as Parmer Lane North, Phase 1 or Segment 3) from SH 29 to FM 3405.
|
Description
|
Construction included a new, interim 2-lane divided rural roadway, asphalt pavement, storm drains, multiple bridge structures, drainage culverts, pavement marking, and signage. The roadway was designed by PBS&J and constructed by Chasco Contracting.
|
Status
|
Construction was completed in March 2007. The road is open for public use.
|