Cedar Park ILA Projects

Location/Description/Status:

The following projects are managed by the City of Cedar Park and partially funded by Williamson County.

A. Cypress Creek Road and US 183 Intersection

Description: The City of Cedar Park and Williamson County are partnering together for the construction of dual left turn lanes in both directions on Cypress Creek Road and will include additional improvements to mobility and safety.

Status:  The construction contract was awarded to Patin Construction.  The construction contract is in the amount of $544,491.  This project is complete.  For updates from the City of Cedar Park, click here and select the “Projects at a Glance” link.

B. Cypress Creek and Lakeline Blvd. Intersection

Description:  The City of Cedar Park and Williamson County are partnering together for the construction of dual left turn lanes in both directions on Cypress Creek Road and will include additional improvements to mobility and safety.

Status:  Design engineer is Binkley & Barfield. The City awarded the construction contract to Smith Contracting. Construction began in June 2015 and was completed in early August 2016.  For updates from the City of Cedar Park, click here and select the “Projects at a Glance” link.

C. CR 272 Overlay from Ronald Reagan Blvd. to RM 1431 and Brushy Creek East Overlay from Arrowhead Trail to Cedar Park City Limits

Description:  The City of Cedar Park and Williamson County are partnering together for an overlay of the existing pavement.

Status:  The contractor is Ramming Paving, and construction was completed in October 2015.

D. Brushy Creek Road and Parmer Lane

Description:  The City of Cedar Park and Williamson County are partnering together for the design and construction of right turn lane modifications.

Status:  The design engineer is Kimley-Horn. Construction was awarded to Smith Contracting. Construction began in August 2016 and was completed in Fall 2016.