Project Description
Location CR 111/Westinghouse Road from Hewlett Loop to just west of FM 1460, approximately two miles in length.
Description Reconstruction of a two-lane roadway to a four-lane roadway.  The proposed roadway will transition from an undivided, four-lane section with a center two-way left-turn lane on the west end of the project to a four-lane divided section on the east end of the project.  Bike lanes will be constructed on both sides of the roadway.  Roadway improvements include construction of enhanced drainage facilities, storm sewer and curb-and-gutter.  Roadway design was completed by Huggins/Seiler & Associates.  A construction contract has been awarded to J.C. Evans Construction Company.
Status Project is complete and open to traffic.

To view a larger version click the picture. To save right click and click "save picture as"