| Location |
On CR 104 from SH 29 to 0.55 miles south of SH 29 and on SH 29 from 0.46 miles west of CR 104 to 0.2 miles east of CR 104. |
| Description |
The CR 104 improvements include construction of a four lane roadway with 11 foot travel lanes, grading, asphalt pavement, storm sewer, curb & gutter, signage, and pavement markings. The SH 29 improvements include widening the road for a two-way center turn lane, a traffic signal at the driveway to the New High School, asphalt paving, signage, and pavement markings. The roadway was designed by Steger & Bizzell and constructed by Cash Construction. |
| Status |
Construction was completed in July 2008. The road is open for public use. |