Location IH-35 from Bud Stockton Loop south of Jarrell, TX to the FM 972 Overpass north of Georgetown, TX
Description The project will implement the conversion of two-way frontage roads to one-way and the removal and reconstruction of existing IH-35 ramps within the project limits.
Status

Design was completed by Binkley & Barfield. An open house was held on Thursday June 30, 2016. A summary of the open house can be found under Project Documents. Construction will be funded by TxDOT. A Bid Opening was held January 9, 2019. Construction is anticipated to begin Summer 2019 and be completed in fall 2020.