CR 119

Location Proposed roadway extension for CR 119/Ed Schmidt Boulevard from Limmer Loop to Chandler Road in Hutto, Texas.
Description    The project will consist of constructing two lanes of a future four-lane roadway with shoulders and a traffic signal at CR 119 and Limmer Loop. The right-of-way footprint will consider the ultimate typical section. 
Status Final design of the interim two-lane roadway with shoulders by Stantec Consulting Services, Inc. (formerly Bury) was completed.  ROW acquisition and utility relocation have been completed. An inter-local agreement with the City of Hutto was approved at the 5/16/17 Commissioners Court meeting. The construction contract was awarded to Joe Bland Construction. Construction began in December 2017 and is anticipated to be completed early 2019. View the project update here.
Contact Email roads@wilco.org or phone 512-846-1190