RM 620 Phase 2

Location From Cornerwood to Deepwood Drive
Description This RM 620 project is approximately 2.74 miles in length and is made up of two segments.

Segment 1 (Cornerwood Drive to Wyoming Springs Drive):
This segment of roadway is a TxDOT project to restripe the existing four lane section to a six lane section.  Sidewalks along the north side of RM 620 in this segment are also planned; however funding has not been identified at this time.  

Segment 2 (Wyoming Springs Drive to Deep Wood Drive):
This segment of roadway is a Williamson County project to widen the roadway from four to six lanes and will include new curb and gutter and a raised median.  This segment will also include left and right-hand turn lanes, culverts, water-quality facilities, retaining walls and construction of sidewalk along the north side of RM 620 to fill in the current gaps.

Status Segment 1: To be completed by TxDOT as funding becomes available.

Segment 2: The bid was awarded to Cox Commercial Construction on November 30, 2016. Construction started on January 13, 2017, and is anticipated to be completed in Spring 2018. 

Oaklands north of RM 620 – Cox Commercial is scheduled to restrict traffic to one lane in each direction starting Monday, January 29.  Traffic will be in this pattern for approximately two weeks while the contractor completes reconstruction of drainage structures and curb and gutter.  

Williamson County’s contractor, Cox Commercial, has scheduled paving operations on the RM 620 project.  Paving is scheduled to take place from February 12 to 15 between the hours of 8 a.m. to 5 p.m.  Paving will take place on the side streets and the hospital driveway.  Oakwood Boulevard will need to be closed between the hours of 9 a.m. to 4 p.m. to accommodate the paving.  A detour will be placed to direct traffic from Oakwood to use Oaklands Drive.  One lane of traffic in each direction will be maintained during the paving of the hospital driveway.   Paving along RM 620 will be outside of the current lanes of traffic.  This schedule depends on the weather. We apologize for any inconvenience this causes our residents.  


Contact Email roads@wilco.org or phone 512-943-1195