RM 620 Phase 2

Location From Cornerwood to Deepwood Drive
Description This RM 620 project is approximately 2.74 miles in length and is made up of two segments.

Segment 1 (Cornerwood Drive to Wyoming Springs Drive):
This segment of roadway is a TxDOT project to restripe the existing four lane section to a six lane section.  Sidewalks along the north side of RM 620 in this segment are also planned; however funding has not been identified at this time.  

Segment 2 (Wyoming Springs Drive to Deep Wood Drive):
This segment of roadway is a Williamson County project to widen the roadway from four to six lanes and will include new curb and gutter and a raised median.  This segment will also include left and right-hand turn lanes, culverts, water-quality facilities, retaining walls and construction of sidewalk along the north side of RM 620 to fill in the current gaps.  

Status Segment 1: To be completed by TxDOT as funding becomes available.

Segment 2: The bid was awarded to Cox Commercial Construction on November 30, 2016. Construction started on January 13, 2017, and is anticipated to be completed in Spring 2018. 

Lane Closures: 

Cox Commercial Construction is working on the placement of roadway flexbase on the south side of RM 620. Contractor also is working on the placement of conduits and foundations for traffic signals. 

Williamson County’s contractor Cox Commercial is scheduled to set various temporary lane closures on RM 620 as part of the RM 620 improvement project from Wyoming Springs to Deep Wood Drive.  The work will occur on Sunday, August 13, Monday, August 14, and Tuesday, August 15, nights starting at 8:00 p.m. and will be complete and all lanes back open to traffic by 6:00 a.m. the next morning.   The closures are necessary for the purpose of paving hot mix asphalt one half mile east and one mile west of the Deep Wood intersection.  Access to driveways and side streets will be maintained at all times.  A police officer will be on the project during this work to manage traffic as needed at the Deep Wood intersection.  All work will be conducted weather permitting.

On August 16, from 8 p.m. to 6 a.m., Cox Commercial is scheduled to set various temporary lane closures on RM 620 for the purpose of shifting eastbound lanes to the south onto the new pavement. The eastbound lanes will be shifted to the south onto the new pavement.  Temporary ramps will be constructed at the intersections and the hospital emergency room driveway to allow eastbound traffic to access the side streets and the hospital driveway.  After this shift, the center turn lane will be removed and eastbound travelers will only be able to access the businesses along the north right of way at the signalized intersections.  All work will begin at 8:00 p.m. and will be complete and all lanes back open to traffic by 6:00 a.m. the next morning. Access driveways and side streets will be maintained at all times.  A police officer will be on the project during this work to manage traffic as needed.  

On August 17, from 8 p.m. to 6 a.m., Cox Commercial, is scheduled to set various temporary lane closures on RM 620 for the purpose of shifting westbound lanes. The westbound lanes will be shifted to the south into the old center turn lane and the inside eastbound lane.  The traffic shift will move the travel lanes to the south to provide a safe work zone along the north right of way.  All work will begin at 8:00 PM and will be complete and all lanes back open to traffic by 6:00 AM the next morning.   Access to driveways and side streets will be maintained at all times.  A police officer will be on the project during this work to manage traffic as needed.   

 

 

Contact Email roads@wilco.org or phone 512-943-1195

Sign up for updates



Submit           
 

Project Map