CR 110 Middle

Location CR 110 Middle (North of Limmer Loop to CR 107)

Description

The project will upgrade the existing two-lane roadway to a three-lane roadway (half of an ultimate six- lane facility). The schematic design and Right-of-Way footprint will consider the ultimate typical section for a six lane divided roadway.

For information on CR 110 North from CR 107 to north of Sam Houston Parkway, click here.

For information on CR 110 South from US 79 to Limmer Loop, click here.

Status Final design of an interim three-lane section has been completed by Kimley-Horn. Right-of-way acquisition and utility relocation coordination are underway. Construction is anticipated to begin in Summer 2017 and be completed in late 2018.
Contact Email roads@wilco.org or phone 512-846-1190

Project Map


View 3.45/4.55 - CR 110 Middle in a larger map