FM 1460 North (North of University/Chandler to Quail Valley Drive)

Location FM 1460 from North of University Boulevard (Chandler Road) to Quail Valley Drive
Description The project will reconstruct FM 1460 to four lane divided section including signal and bridge improvements.
Status The project was awarded on August 28, 2014 by the Texas Department of Transportation to OHL, Inc. ROW Acquisition is complete. Construction is underway and is anticipated to be completed in Summer 2018.

The FM 1460 project in Williamson County has introduced newly constructed lanes for drivers. This design modification has changed the way motorists drive on FM 1460 between Quail Valley Drive and SE Inner Loop. 

During the next phase of construction, TxDOT crews will be constructing the new northbound FM 1460 mainlanes from SE Inner Loop to University Drive.  Crews will also be constructing Westinghouse Drive, east of FM 1460. The project is expected to continue until spring 2018.  

Contact Email roads@wilco.org or phone 512-943-3370

Sign up for updates


Project Map