CR 305 at IH35 Phase 1 Bridge Replacement

Location CR 305 at IH 35
Description The project will replace the existing two lane bridge at the intersection of CR 305 and IH 35.
Status Design underway by H.W. Lochner, Inc. Construction will be scheduled once state or federal funding has been identified. An open house was held on Thursday June 30, 2016, presenting proposed improvements to CR 305 at I-35, Ronald Reagan Blvd. at I-35, and Frontage Roads between Bud Stockton Loop and FM 972 in Jarrell, TX.  A summary of the open house can be found under Project Documents. An inter-local agreement with the City of Jarrell was approved at the the Commissioners Court meeting on March 7, 2017. All right-of-way has been acquired. 
Contact Email roads@wilco.org or phone 512-943-3370

Project Map